Upcoming Sewer Main Replacement Project
WQZW222, Enumclaw information radio AM1650.
On August 1 work will begin on a sewer main replacement project on City property along the east side of SR410 from Warner Avenue north to Roosevelt Ave. Approximately 3200
feet of 36” and 30” sewer will be installed, beginning at the south end of the project and working north. Warner Avenue will be closed at the intersection with SR410 when work is
being done affecting Warner Avenue. Trucks will access the work area off Warner Ave and exit onto SR410 at different locations as the work progresses northward.
The project is funded by the City sewer utility and is expected to extend into late October. If you have any questions or concerns please contact Lance Talmadge at 360-615-5740.
This message will be repeated.